How can I perform network studies with one breaker pole open?

Category:
Power Equipment Models
Answer

PowerFactory is able to calculate single-phase interruptions within the short-circuit calculation (complete method) and in the transient simulation.

Another option is to connect a three phase line via three ideal single phase lines to its terminals. You then can open each of the single phase lines, and hence each of the phases individually, also in load flow, harmonics etc.